Physical and Financial Accomplishment Report

Showing 1-20 of 2,082 items.
#Project NameReport DateAllocation (ARP)Allocation (FTM)Releases (ARP)Releases (FTM)EG (Male)EG (Female)
1Taal Lake Circumferential Road Jun 30, 2016200000000.00(not set)200000000.00(not set)26(not set)
2Batangas-Tabangao-Lobo Road Jun 30, 201655949000.00(not set)55949000.00(not set)20(not set)
3Batangas-Lobo Road K0115+360.00 – K0116+1082.00, K0114+000.00 – K0115+239.00Jun 30, 201679685000.00(not set)79685000.00(not set)24(not set)
4Talisay-Laurel-Agoncillo RoadJun 30, 201679000000.00(not set)79000000.00(not set)21(not set)
5MSR JCT.Lopez-Catanauan Road Jun 30, 2016125935000.00(not set)125935000.00(not set)24(not set)
6SUMULONG HIGHWAYJun 30, 2016110750000.00(not set)110750000.00(not set)20(not set)
7Marikina-Infanta Road Jun 30, 201669000000.00(not set)69000000.00(not set)25(not set)
8Sariaya Bypass RoadJun 30, 2016166800000.00(not set)166800000.00(not set)31(not set)
9 Lopez Bypass Road, Lopez, Incl. ROW (GAA 2015)Jun 30, 2016100000000.00(not set)100000000.00(not set)26(not set)
10Construction of Lucena-Diversion Talao-Talao Port Road Jun 30, 2016169000000.00(not set)169000000.00(not set)20(not set)
11Lobo- Malabrigo-Laiya-San Juan Road Jun 30, 2016150000000.00(not set)150000000.00(not set)18(not set)
12Construction of Gravel Road - Maragondon Bypass RoadJun 30, 2016150000000.00(not set)150000000.00(not set)36(not set)
13Macalelon Small Reservoir Irrigation ProjectMar 31, 2019404045000.00(not set)145156000.00(not set)(not set)(not set)
14Quipot Irrigation ProjectMar 15, 20191449500000.000.001099000000.000.00(not set)(not set)
15South Luzon Expressway Phase 2, Toll Road 4 (TR4) ProjectMar 31, 2019(not set)(not set)(not set)(not set)(not set)(not set)
16Construction of Atulayan - Bislian - Pamatdan FMRDec 31, 2018156251697.07(not set)9375101.82(not set)(not set)(not set)
17Concreting of Camflora FMRDec 31, 201873977064.37(not set)14795412.87(not set)(not set)(not set)
18Sustainable Livelihood ProgramDec 31, 2018315630000.00(not set)315630000.00(not set)(not set)(not set)
19LRT Line 2 East Extension Project Dec 31, 20188262449442.00(not set)8262449442.00(not set)(not set)(not set)
20Seedling Production (Cavite Province)Mar 31, 2019175000.00(not set)175000.00(not set)94