Status of Projects Encountering Problems

Showing 1-10 of 10 items.
#Project NameFindingPossible Reason/ CauseRecommendation
1Quezon Port Development ProjectOn scheduleN/AFast track remaining activities to achieve an accomplishment of ahead of schedule
2Construction of Wharf Slight delay in construction incremental weather condition during the last month of the year 2015 adjust the project timeline
3Quezon Port Development ProjectThe project was completed on schedule (April 10, 2016)The project started at the contractors own risk but high tide prevent the project from completing ahead of time.For turn-over and Acceptance
4Tingloy PortFor rectification of minor defectsImproper use of pier by boat vessel's rampRectification before issuance of project completion
5Quipot Irrigation ProjectDelay of contract schedule of contractors
Unfavorable weather condition
Suspension of project contract due to bad weather condition
6Light Rail Transit (LRT) 1 Cavite ExtensionAdditional row acquisition are needed
Due to C1A option that requires adjustment of Line 1 Extension Alignment to avoid clashing with C-5 alignment.

Appraisal of additional lots
Preparation and approval of subdivision plans
Negotiate to property owner through a letter offer
7Light Rail Transit (LRT) 1 Cavite ExtensionRelocation of Utilities
Utility Relocation is not in full swing because of the processing of MOA between LRTA and Utility Agencies/Companies. (Telcos & Maynilad)

Meralco (On-going relocation of Electrical Post and Conductors)


On-going preparation of MOA
8LRT Line 2 East Extension Project Delayed implementation1. Procurement issues/delays
2. Unforeseen site condition
3. Political intervention
1. a. Thorough review of documents
b. Adjustment in bidding requirements
c. Close coordination with all concerned
2. a. Advance and close coordination with LGUs and utility
b. Constant monitoring and supervision of works and other
c. Close coordination with all concerned.
3. a. Strong representation by top management.
b. Close coordination with all concerned.
9LRT Line 1 South Extension ProjectDelay in ROW acquisition of additional lots1. Additional ROW due to C1A option that requires adjustment of Line 1 Extension Alignment to avoid clashing with C-5 alignment.
2. Additional ROW due to change in station location.
To secure approval of MOA between LRTA and Philippine Reclamation Authority (PRA) regarding the affected additional lots.
10LRT Line 1 South Extension ProjectDelay in Relocation of UtilitiesDelay in the approval of MOA between LRTA and utility providersContinuously monitor the approval of MOA, attend coordination meetings with the stakeholders and provide pertinent documents as required.